Demonstration Plant Equipment Design and Scale-Up from Pilot Plant of a Leaching and Solvent Extraction Process

Arroyo, Fatima; Fernandez-Pereira, Constantino; Bermejo, Pilar

Abstract

Germanium recovery from coal fly ash by hydrometallurgical procedures was studied at the pilot scale (5 kg of fly ash/h). Results were used to design the equipment of a demonstration-sized plant (200 kg of fly ash/h). The process is based on hydrometallurgical operations: firstly a germanium extraction from fly ash by leaching and a consequent Ge separation from the other elements present in the solution by solvent extraction procedures. Based on the experimental results, mass balances and McCabe-Thiele diagrams were applied to determine the number of steps of the solvent extraction stage. Different arrangements have been studied and a countercurrent process with three steps in extraction and six steps in elution was defined. A residence time of 5 min was fixed in both the extraction and elution stages. Volumetric ratios in extraction and stripping were: aqueous phase/organic phase = 5 and organic phase/stripping phase = 5, so a concentration factor of 25 is achieved. Mixers and decanters were completely defined. The maximum extracted and eluted germanium was estimated and a global efficiency of 94% was achieved. The cost-effectiveness of the equipment was estimated using the Lang factors.

Más información

Título según WOS: ID WOS:000357152700011 Not found in local WOS DB
Título de la Revista: Minerals
Volumen: 5
Número: 2
Editorial: MDPI
Fecha de publicación: 2015
Página de inicio: 298
Página final: 313
DOI:

10.3390/min5020298

Notas: ISI